The Biography of Chicago’s Marina City

Laying the foundation
November 1960

Marina City construction site. Portland Cement Association (1961).

(Above) Early view of Marina City construction site from the south. Dearborn Street Bridge under construction at left. State Street Bridge at right.

Once ground was broken, crews went to work on the foundation. As complex as Marina City was above ground, it was going to be challenging underneath, too.

In late November 1960, architectural drawings for the east tower were not complete but they were done enough for the foundation to be put in.

This mostly consisted of 80 caissons (154 counting the west tower), each buried 115 feet down, past layers of fill, gravel, three levels of water, and a variety of clays, into a limestone shelf that stretches to Niagara Falls.

Each caisson consisted of a steel tube, called a casing, which was closed at the bottom with a plug. The casing is driven into the ground to a required depth and filled with concrete, forming a “pile” inside the casing.

Drilling a shaft for each caisson was “Big Bertha,” the world’s largest drill. Owned by Case Foundation Company, it was eight stories tall and weighed 125 tons. It could drill a hole five-and-a-half feet wide and 200 feet deep.

Pile diagram.
Aerial view of east tower foundation. Portland Cement Association (1960). The maximum diameter of piles varied from 24 to 66 inches. Every 24 hours, four casings with reinforcing bars were drilled to bedrock, filled with concrete, and capped with a heavy steel plate.

This was done around the clock until March 1961.

There are three concentric rings of piles. The central core is constructed over the inner ring but the outer rings take most of the load. The central core is 32 feet in diameter. The thickness of the core walls decreases from 30 inches at the base to 12 inches at the top, 588 feet above the base.

(Left) Aerial view of east tower foundation.

Dr. Ralph B. Peck With Mueser Rutledge Consulting Engineers handling the foundation engineering, the foundation consultant was Dr. Ralph B. Peck (1912-2008), the engineer who literally wrote the book on soil mechanics.

Peck was born in Canada to American parents, earned a Doctor of Civil Engineering in 1937, was a lab assistant to noted civil engineer Arthur Casagrande, and from 1939 to 1942, he was an assistant engineer on the Chicago Subway Project.

(Left) Dr. Ralph B. Peck

Since 1942, Peck had been a teacher in the civil engineering department of the University of Illinois at Urbana-Champaign. He would eventually be professor emeritus of foundation engineering at the university and known as “the godfather of soil mechanics.”

In 1948, Peck co-authored the most influential textbook in geo-technical engineering, Soil Mechanics in Engineering Practice. In 1953, he co-authored the widely used textbook, Foundation Engineering.

By February 1961 there was already a conflict with a nearby construction project. Engineers determined that caissons could not be sunk at Marina City and the new Dearborn Street Bridge at the same time. Because of soil conditions, it could damage buildings and streets. A schedule had to be worked out between the two projects. For two months in early 1961, construction of the west tower core was delayed because of work on the bridge by the city.

(Right) Dearborn Street Bridge under construction in 1960.

Dearborn Street Bridge construction (1961).

On February 16, 1961, a construction fund account was opened with $20 million at Continental Illinois National Bank and Trust Company. Interest in Marina City from prospective renters was strong around this time, with 2,000 inquiries received for 896 apartments.

The next day, the city council’s building and zoning committee heard Marina City Building Corporation’s request for a zoning change to allow it to build residences on property on which only businesses were currently allowed. Work was underway by special permit.

Last updated 16-Jun-14

Next story: Marina City starts to rise