For a brief time in the 1960s, Marina City was the world’s tallest structure made of reinforced concrete. The cost to maintain the concrete has never been cheap. In the early 1990s, Marina Towers Condominium Association spent $1.7 million over three years to repair the concrete and repaint balconies and vertical surfaces.
The cost was $2 million in 2008 when the condo association needed to repair problem areas identified in 2006 and 2007 by the structural engineering firm Wiss, Janney, Elstner Associates, Inc.
Over the next three years, weakened concrete would be cut open down to the rebar, sandblasted, sealed with epoxy, then covered with concrete in which adhesive had been mixed. Railings would be repaired, too, and unit owners had an option of a polyurethane membrane that would cover the concrete slab on their balcony.
The membrane would cost the unit owner $1,250 for a full balcony and $900 for a half-balcony. All apartments at Marina City have a full balcony. One-bedroom units have an additional half-balcony, and two-bedroom units have one-and-a-half additional balconies.
While waterproof, the membrane would not level the balcony floor and prevent “ponding,” the accumulation of small pools of water and an ongoing issue at Marina City. According to property manager David Gantt, when the concrete was finished in the early 1960s, an error with how floor drains were placed resulted in uneven balcony surfaces. Marina City architect Bertrand Goldberg, he suspects, “must have had a fit.”
Gantt said that in more recent years, experiments had been done to see how the ponding could be fixed. “We tried to see if it would be possible to create a little [water collection] trench to the drain but the engineers determined that the rebar would be too close to the...trench. The rebar would then rust. We tried lightweight concrete and determined that...was not entirely acceptable as the drains were still too high. The cost would be over $12,000 per balcony...That’s $12,000 times 1,248 balconies.”
Repair of the massive concrete exterior of both towers began during the week of September 20, 2009, starting with the west tower. With sidewalk canopy barricades protecting pedestrians on Dearborn Street from any falling debris, workers moved up and down the towers from four “swing stage” suspension scaffolds.
Suspended hundreds of feet above Dearborn Street, workers for Quality Restorations, Inc., would visit 16 balconies on each of 44 residential floors in two towers between October 2009 and December 2010.
Ride-along with the Gonzales brothers
Suspended just beyond the 29th floor of the west tower, brothers Cruz and Hernando Gonzales work from a “swing stage” scaffold suspended approximately 260 feet above Dearborn Street.